About the Project

West Virginia Department of Transportation (WVDOT), in cooperation with the Federal Highway Administration (FHWA), is improving an approximately 1.7-mile section of Jefferson Road (WV 601) from US 119 to US 60. These needed upgrades will improve safety, reduce congestion and improve opportunities for economic development. 

Construction will widen Jefferson Road to five lanes, add a new roundabout at Kanawha Turnpike, and build a new overpass bridge that spans Pennsylvania Avenue, CSX Railroad, Davis Creek and Kanawha Turnpike. 

Background

Jefferson Road serves as a major connector between the communities and businesses west and southwest of Charleston. A traffic study conducted in 2016 concluded excessive traffic congestion along the Jefferson Road corridor would overwhelm the roadway’s capacity by 2030. A safety study found that the crash rate along this 1.7-mile section of Jefferson Road had four times the average crash rate for similar roadways across the state. These issues coupled with the growing needs of the region reaffirmed the need to improve Jefferson Road, which regional planning studies have recommended for this corridor since the 1990s. 

Jefferson Road Project Map

Project Map. Click Image to Enlarge.

Project Details

Phase 1

Construction consists of new drainage/asphalt to rebuild and widen Jefferson Road between Kanawha Turnpike and Dapplewood Drive while maintaining two lanes of traffic. Also, construction will begin on the bridge that will cross Kanawha Turnpike and CSX Railroad in this phase with minor excavation, new drainage, and structure work included (area highlighted in yellow).

Phase 1 Map. Click to Enlarge.
Phase 1 Map. Click to Enlarge.
Phase 2A

Traffic will be pushed to the West towards the shoulder of Jefferson Road between Dapplewood and Corridor G to provide room for Phase 2A construction while maintaining two lanes of traffic. Access to all city streets and drives will be maintained for traffic during this phase. Construction in this phase that widens Jefferson Road to the East includes major excavation, new drainage, utility relocations, and new asphalt. Bridge work that started in Phase 1 will continue through this phase (area highlighted in yellow).

Phase 2A Map. Click to Enlarge.
Phase 2B

Two lanes of traffic will relocate to the newly constructed roadway built in Phase 2A between Dapplewood and Corridor G to provide room for Phase 2B Construction. Access to all city streets and drives will be maintained for traffic during this phase. Construction in this phase rebuilds the west side of Jefferson Road. This work includes minor excavation, new drainage, utility relocations, and new asphalt. Bridge work that started in Phase 1 will continue through this phase (area highlighted in yellow).

Phase 2B Map. Click to Enlarge.
Phase 3

Traffic will relocate onto the new alignment of Jefferson Road from Corridor G to MacCorkle Ave. Minor roadway construction will be completed in this phase to complete tie in work at the roundabout and city streets.

Phase 4

Traffic patterns will maintain on the new alignment of Jefferson Road from Corridor G to MacCorkle Ave. Minor roadway construction will be completed in this phase to complete tie in work at the roundabout and city streets.

Design and Construction

Funding

West Virginia’s Roads to Prosperity highway construction and maintenance program allowed WVDOT to free up existing state and federal funding for the Jefferson Road Improvement Project. The total cost for design and construction is $46.8 million.

Construction Schedule

Season and YearProject PhaseDetails
Spring 2022 – Summer 20220Initial Construction Phase 
Summer 2022 – Fall 20221Draining and widening of Jefferson Road between Dapplewood and Kanawha Turnpike
Fall 2022 – Summer 20232AExcavation, drainage, and widening of Jefferson Road to the east
Fall 2023 – Winter 20232BExcavation, drainage, and widening of Jefferson Road to the east
Summer 2022 – Winter 20231 & 2A/2BBridge and roundabout work
Spring 2024 – Summer 20243Tie in work at the roundabout and city streets
Summer 2024 – Fall 20244Tie in work to Kanawha Turnpike and city streets